Inside Unit 3 & 4 at Reedswood Park

Project

Unit 3 & 4 Reedswood Park

Client ID card icon

Client Name

X-cel Construct
Location Icon

Location

Walsall
Project Value Growth Icon

Project Value

£1.83m

Over a high paced 28 week period Cavish completed all groundworks for two distribution centre units at 35,000sqft and 75,000sqft. Following on from and Earthworks enabling contractor, Cavish completed the following:

  • Foundations and installation of precast concrete retaining wall solution complete with drainage.
  • Traditional pad foundation arrangement.
  • Extensive large diameter drainage, inc. installation of 2 full retention oil interceptors.
  • Fully validated gas membrane to CS2 condition.
  • Brushed external service yard works.
  • A new footpath to existing highway.
  • Block paved car parks to both units.
  • Builders working connection with all services to the buildings.

 Cavish were able to secure and deliver successfully further works internally, this included FM2 power floated floor slabs, utilising armour joints.

No items found.
Cavish Civil Engineering - Logo
Follow our journey

Accredited Contractors

We are proud to hold CHAS Elite, Construction Line Gold Accreditations and Acclaim Accreditation for Health & Safety.
Cavish Civil Engineering - CHAS CertificateCavish Civil Engineering - Constructionline CertificateCavish Civil Engineering - Acclaim Certificate